Cabinet considered a proposal to award a construction contract for a new care home and 11 supported-living bungalows at the former Innovation Park Medway South site, with borrowing now forecast at £37.7 million after cost reductions.

Medway Council’s Cabinet met on 17 November 2026 to consider awarding a design-and-build contract for a new 80-bed care home and 11 adult social care units (ASCUs) at the former Innovation Park Medway South site, following the completion of RIBA Stage 3 design work.

What is being built

The proposed development is described in the papers as a landscape-led scheme. The care home would provide 40 beds on the ground floor for residential, dementia, nursing and complex care, and 40 beds on the first floor designed flexibly for discharge-to-assess, NHS leasing or hospice provision. A second floor would house back-of-house functions including a kitchen, laundry, staff rooms and a rooftop garden. The 11 bungalows, a mix of one- and two-bedroom units, are intended for people whose care needs have reduced and who are moving towards more independent living.

Procurement and cost

An open tender was run over ten weeks and five submissions were received. The papers state the recommended contractor achieved a weighted evaluation score of 76.39%, comprising quality at 45.75%, cost at 25.64% and social value at 5.00%. The contractor’s name is contained in an exempt appendix and was not published in the public papers.

Officers reported an improvement in the scheme’s affordability, from the original £44 million position to £40 million. A Better Local Resilience Fund award of £2 million and a reduction in project management costs of £300,000 have reduced the borrowing requirement to £37.7 million. The RIBA Stage 3 cost plan forecast an overspend on the project of approximately £1.5 million, and officers said they would work with the appointed contractor to explore value engineering opportunities. The papers say the highest-scoring tender gives a more definitive budget picture that delivers within the £44 million approved by Full Council in November 2025, and that there is no intention to seek further funding.

Why the council says it is needed

The papers cite Medway’s population aged 65 and over as projected to grow by 24% by 2040, with the 85-and-over cohort expected to rise by 55%. Demand for dementia care is forecast to increase by between 38% and 46%. The papers note that during 2026 one Medway care home closed following an inadequate regulatory rating, resulting in the loss of 35 beds. Since 2021, two older persons’ care homes have closed with a loss of 77 beds, while three new homes have opened providing 213 beds — a net gain of 136 beds. Officers stated that demographic growth means Medway would still require an additional 54 care home beds by 2030 simply to maintain the current ratio of beds to the population aged 75 and over.

The papers describe the development as a strategic demand-management intervention, noting that the council is already incurring costs from insufficient local capacity, including above-band placement costs, specialist bariatric placements and premium-priced discharge placements. An independent appraisal cited in the papers found the scheme becomes financially viable after approximately 27 years and maintains a positive financial position over a 50-year appraisal period.

Next steps

Cabinet was asked to approve progression to RIBA Stages 4 to 7 and to award the contract. A start on site is programmed for January 2027. Planning permission was due for a decision in November 2026, described as one month later than the original programme. The council had not published the minutes of the meeting at the time of writing, so the committee’s decision is not yet on the public record.

Sources